Our Services

We provide a range of consultancy services for the concept, planning and implementation of jacked structures. The key to successful installation is in  integrating the permanent work design and  the temporary  works that need to be undertaken during installation. These have to be designed to minimize risk and ensure work proceeds rapidly with the least delay and minimum soil movement.

Our services are provided to owners, consultants and contractors. 

Conceptual Design

Conceptual design, planning and budgets to identify viable technical and economic approaches for a jacked installation which meet the client’s requirements is where many projects fall short of ideal..

The importance of conceptual engineering  is highlighted by the figure. This shows the relative cost impact that can be achieved as a project moves from concept to execution.

The preconstruction phase represents the smallest percentage of the overall project cost but has the greatest impact on the level of the final costs.

With our extensive range of methods and techniques we can develop designs to meet the needs of the client and its location. Our approach is to gain an in-depth understanding of the site, the soil conditions, the client's needs and the restrictions and requirements of third parties such as rail and highway authorities. Only then can we develop a concept which often requires a combination of methods rather than a set approach.

The importance of developing a concept that will fully take into account the soil and ground  water  conditions to ensure safe working and minimization of soil movement is essential and  we have in house highly qualified geotechnical expertise.

Design Development

The characteristics of situations where jacked structures are appropriate include:

  • Minimizing disruption to the surface facility is a key consideration.
  • The owner of the surface facility will not allow disruption.
  • There are stringent limitations on soil movement
  • The occupation period needs to be minimized.
  • The cover is too shallow for traditional tunneling.
  • The drive length is uneconomic for traditional tunneling
  • Environmental disturbance has to be avoided.
optioneering

The range of possible solutions are extensive  and each one is unique to the location, conditions and restrictions.

The chart graphically  sets out options for installing underpasses below rail tracks where limited possession is possible and where not.

Developing the concept into a detailed engineering scheme and program requires the permanent works design and the methods of installation to be integrated. This requires close cooperation between the respective design teams. Work is often undertaken on a "Design and Construct" basis and the lead contractor will be closely involved.

The installation stage is the prime concern as once work is underway there is one chance only of getting it right. Our principal function at the design stage is to ensure that all aspects of the installation are designed and planned to ensure this happens.

Some of the temporary aspects that we design and develop in detail  are:

  • Settlement evaluation
  • Settlement mitigation and compensation grouting
  • Soil stabilization
  • Settlement monitoring
  • Entry and exit procedures
  • Shield design for face control and stability  
  • Shield face operation to maintain face stability
  • Soil drag reduction by lubrication, drag sheets and ropes
  • Jacking load calculations and jacking load reduction by lubrication and  interjacks
  • Jacking reaction slabs and transmission of jacking loads onto the structure
  • Jacking installations
  • Incorporating the needs of the installation works into the permanent design.
  • Required high standards for finishes and accuracy of  permanent structures cast at site
  • Quality assurance on precast units to ensure meeting accuracy and finish standards

We work with consultants who are undertaking the permanent design and provide inputs on such issues as:

  • Incorporating the needs of the installation works into the permanent design.
  • Loads arising during installation on the permanent structure 
  • The required high standards for finishes and accuracy of  permanent structures cast at site
  • Quality assurance on precast units to ensure meeting accuracy and finish standards

Installation

We provide various levels of management of the installation works. 

Our work involves developing highly detailed procedures and programs for the installation. With a set window of installation everything needs to be in place and operational to ensure that work is completed within the time frame. 

Jacking  large structures such as boxes and decks require  special measures to avoid settlement and heave due to friction and soil movement. We have developed our own specialist  lubrication methods as well as using established methods such as drag sheets and ropes. (James Thomson developed the drag sheet some years ago when working for a major UK contractor)

We work closely with consultants, contractors and specialist sub-contractors throughout the planning and installation.

We provide expert and experienced engineers both in the lead up and during installation to monitor the operations and ensure that work is proceeding as planned and to the required standards 

Risk Minimization

Risk minimization is a key part of our approach. Our projects are  usually in high risk locations. Every project is unique and has its own specific characteristics and uncertainties. Each situation must be judged on this basis.  The potential consequences and the likelihood of any risk event occurring need to be assessed at every stage of the project

We believe management of risk should be based on risk identification not on avoidance. 

Unlike some tunneling systems the risks of a serious collapse with jacked installations are virtually eliminated. In  jacked installations the shield is  designed to advance ahead of excavation and  to deal with any local soil movement at the face. The permanent structure is continually advanced  behind the shield ensuring that the excavation is always fully supported. 

Where the risk of unstable ground conditions exists appropriate pre- stabilization techniques are used.

These basic built in features ensures that both workers and clients are not exposed to collapse and the consequences.

Expert Witness 

Our consultants have extensive experience in undertaking Expert Witness services  in disputes involving the underground infrastructure, tunneling and jacked installation